Sample deliverable · US Letter 8.5×11
WASATCH GRID ELECTRICAL
Electrical critical-path partner
Power on schedule.
Zero thermal incidents.
Zero thermal incidents.
Substation through energization for AI data-center campuses · Northern Utah
Prepared for: Hyperscale EPC — Intermountain region
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.Capabilities dossier
Wasatch Grid ElectricalExecutive summary
Why us, in one page
The Northern Utah electrical prime that has already energized a 400 MW campus on schedule — substation through energization, sequenced to your cooling ramp, so the schedule never waits on electrical.
- 01Substation, switchgear, and medium-voltage delivery with commissioning records on file.
- 02Energization sequenced to the cooling and load ramp — a plan attached, not a promise.
- 03Backup power proven at <50 ms transfer under full load at comparable scale.
- 04EMR 0.71 (3-yr average); zero lost-time incidents; $40M single / $120M aggregate bonding; named foremen on day one.
The ask: a 30-minute scoping call before the electrical package is awarded.
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.2 / 8
Wasatch Grid ElectricalCapabilities & procurement
Scored the way procurement scores you
Every claim has proof attached.
| Scope | Standard judged against | Proof attached |
|---|---|---|
| Substation + switchgear | IEEE C37 / NETA acceptance | Commissioning records, as-builts |
| Medium-voltage distribution | 4–35 kV, NEC + utility spec | Three comparable installs |
| Backup power integration | <50 ms transfer, full load | Witnessed transfer test report |
| Energization sequencing | Phased to cooling/load ramp | Sequence plan + prior schedule |
| Safety + bonding | EMR / OSHA 300A | 3-yr rate, zero lost-time |
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.3 / 8
Wasatch Grid ElectricalProof of relevant scale
We have already done this
Scope
$18.4M electrical prime · 400 MW · 4 buildings · 2024 · EMR 0.68 at the time
Challenge
Multi-phase campus; switchgear and tie-in across four buildings while cooling was still being finalized.
Approach
Sequenced electrical to the cooling deployment; redundant feeds per building; coordinated parallel generator testing with the utility.
Result
Full campus energized on schedule. Zero thermal incidents. 4 MW backup per building at <50 ms transfer.
Reference
Project Director, hyperscale operator — available under NDA.
Scope
$6.1M electrical prime · 35 kV transmission extension · 2023
Challenge
Utility substation two miles out; transmission extension needed across permitted land.
Approach
Led right-of-way, environmental, and utility coordination as pre-work; mobilized the line crew on permit clearance.
Result
Switchgear live in 16 weeks; campus online ahead of server delivery; retained as lead electrical partner for the next phase.
Reference
EPC construction lead — available on request.
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.4 / 8
Wasatch Grid ElectricalEnergization sequence
Power phased to your ramp
The plan, before a crew mobilizes.
| Phase | Trigger | Gate before next phase |
|---|---|---|
| P0 — Utility tie-in | Interconnect approval | Protection + relay test signed |
| P1 — Building A live | CRAC commissioning A | Load bank to 60%, thermal stable |
| P2 — Building B + backup | Generator witnessed test | <50 ms transfer, full load |
| P3 — Full campus parallel | All halls accepted | Utility parallel-op sign-off |
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.5 / 8
Wasatch Grid ElectricalRisk register
Your failure questions, pre-answered
| Risk | Likelihood / impact | Mitigation on record |
|---|---|---|
| Interconnect approval slips | Med / High | Pre-work at LOI; utility desk engaged early |
| Long-lead transformer delay | Med / High | Order at award; alternate vendor qualified |
| Thermal excursion at ramp | Low / High | Phased gates; load-bank proof each step |
| Crew availability at peak | Med / Med | Named foremen; second crew standby clause |
0
Lost-time incidents, 3 yr
<50ms
Backup transfer, full load
100%
On-schedule energization
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.6 / 8
Wasatch Grid ElectricalCapacity & bonding
What gets checked before anyone reads page two
The gate, already cleared.
| Screen | Wasatch Grid | Why it gates the award |
|---|---|---|
| Surety / bonding | $40M single · $120M aggregate | No bond, no bid at hyperscale |
| Financial strength | Audited statements; LOC in place | A thin sub is schedule risk |
| Manpower depth | 140 electricians · 9 named GF/foremen | The ramp cannot wait on hiring |
| Equipment | Owned line trucks, cranes, test gear | Rentals slip the critical path |
| Licensing footprint | UT · NV · ID · WY (master electrical) | Multi-state campuses need coverage |
| Certifications | NETA · NICET III · OSHA 30 | Procurement disqualifies without |
| Safety | EMR 0.71 (3-yr avg) · 0 lost-time | The owner’s insurer screens EMR first |
$120M
Aggregate bonding capacity
0.71
EMR · 3-year average
140
Electricians on the bench
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.7 / 8
WASATCH GRID ELECTRICAL
The ask
Thirty minutes, before the electrical package is awarded.
We are ready to own the power critical path. The rest is a conversation.
estimating@wasatchgrid.example · (801) 555-0148
Illustrative sample. Wasatch Grid Electrical is a fictional company; a real Playbook is produced in the client’s own brand.8 / 8
1 / 8
We design, build, and run digital systems for the science, aerospace, and biotech industries.
Capabilities
Industries We Serve
Aerospace & DefenseBiotechnologyMedical & HealthcareManufacturingFinancial ServicesConsumer ProductsEnterprise Software
© 2026 Bttr. All rights reserved.